The project progressed smoothly, thanks to strong performance and cooperation from the specialist contractors. Vextrix’s expertise in CDM regulations and site risk assessments proved invaluable. The team used their experience and knowledge to advise the client on the buried services checks required for a Hiab lifting operation, performed above existing drainage systems. This precaution, supported by a GRP (ground-penetrating radar) survey, ensured the safety and stability of lifting equipment, preventing potential ground collapse, equipment damage, or injuries. The survey and lifting plan ensured the operation was carried out safely and efficiently.
The scope of services included site visits to conduct risk assessments and participation in weekly progress meetings held on Microsoft Teams. The team maintained close communication with the ISS project managers throughout the project, ensuring all CDM actions were tracked and addressed effectively.